Azerbaijan completes preparations for beginning of heating season
6.11.2012

JSC Azeristiliktedzhhizat (national operator for the supply of heat) will open the heating season in Azerbaijan from November 15, the company told.

There are residential houses, kindergartens, schools, health and other social facilities in Baku and regions of Azerbaijan on the balance shit of the company.

The JSC said in particular, work on construction, repair and replacement of heating lines, construction and repair of boilers, as well as installation and repair of pumps were carried out. All necessary work in preparation for the winter season has already been carried out and the JSC is ready to open the heating season since the middle of this month.

"All the necessary work was carried out in order to provide consumers with high heat. Currently, all of the equipment is in a state of readiness," the JSC added.

A number of new boilers, which construction has been completed, will also be commissioned by mid-month.

It was planned to commission these facilities on mid-December in accordance with the schedule, but all the necessary work were carried out, and they will be able to start functioning in mid-November," the JSC noted.

At the moment, work is underway to connect new boilers to natural gas.